Due to the impact of Covid-19 on our supply chain, we have been experiencing difficulties in sourcing the specialist materials and equipment we require to make the connections between the existing and new pipelines that have been installed under the river near the Quay in Sandwich. Coupled with the recent inclement weather, we have therefore had to delay this element of our work until next week (w/c 15th June) at the earliest.
This will have a knock on impact on the timeline for completion of our repairs and the subsequent planned re-lining of the sewer pipes running under the A256 near Discovery Park.
As previously indicated, in order to enable the connections to take place, the pumping station will need to be shut down for a period of up to 36 hours for each connection (north and south), during which we will need to use tankers to manage flows.
We will be using up to 15 tankers during each shutdown period so we now expect to have to implement a noticeable increase in tanker activity during the period 15th – 26th June.
Supporting information will be shared via local media and social messaging to ensure local residents are aware of the delay. We will also update our dedicated webpage here
We will continue to implement measures for minimising the impact of the tankers when they are needed – using as few as possible, keeping them out of the town when possible, engines only running when necessary, and imposing a strict 20mph speed limit (10mph overnight).
Completing our works
Our teams have been working extremely hard to maintain progress and complete the installation of the new pipelines as quickly as possible whilst working within the restrictions placed upon them by current guidelines.
Subject to any further unforeseen delays, or long periods of inclement weather, we now expect to complete our works by mid-July, with full demobilisation by end of July.
Re-lining works on the A256
To provide additional resilience to the two sewer pipe running underneath the A256 by Discovery Park, we will be undertaking re-lining works following the conclusion of our repairs at the Quay. We expect our work to begin in mid-July for 2 -3 weeks. The road will remain open throughout however single lane closures will be required to ensure the safety of our workforce and other road users. Further information will be provided in due course.
Get in touch
If you have any questions or concerns, you can contact our Customer Service Centre on 0330 303 0368 (24 hours – calls charged at local rate) or fill out our online form.
ENDS
We’re making good progress with our emergency repair works in central Sandwich, near the Quay.
Our teams continue to follow the advice and recommendations from the Government and health authorities to ensure that they are able to continue working safely while respecting social distancing measures.
We’d like to thank the local community for their patience and understanding while we carry out this essential work.
What’s happening ?
We’ve drilled two new independent river crossings in central Sandwich, near the Quay; one to replace the damaged Bulwark main, serving Sandwich, and a second to provide additional resilience for the Golf Road main, serving Deal, which also runs underneath the river.
Subject to suitable weather conditions, we are expecting to make the connections between the existing and new pipe lines during the first two weeks of June. In order to enable the connections to take place, the pumping station will need to be shut down for a period of up to 36 hours for each connection (north and south), during which we will need to use tankers to manage flows.
We will be using up to 15 tankers during each shutdown period so there will be a noticeable increase in activity during the period 1st - 15th June when the connections takes place.
A letter is being sent to all Sandwich residents to raise awareness of the increase in tanker traffic on the town’s roads, accompanied by supporting media and social messaging. We continue to host a dedicated page on our website here
We will continue to implement measures for minimising the impact of the tankers when they are needed – using as few as possible, keeping them out of the town when possible, and imposing a strict 20mph speed limit (10mph overnight).
Completing our works
Despite significant changes to working practices brought about by the current situation, and a number of unexpected delays encountered along the way, our teams have been working extremely hard to maintain progress and complete the installation of the new pipelines as quickly as possible.
Subject to any further unforeseen delays, or long periods of inclement weather, we expect to complete our works by early July with full demobilisation by mid-July.
Supporting customers during Covid-19
We’ve expanded the support available for customers during the current pandemic. These measures are in addition to the support we already offer. For further information, please see the attached pdf or visit our website here.
Get in touch
If you have any questions or concerns, you can contact our Customer Service Centre on 0330 303 0368 (24 hours – calls charged at local rate) or fill out our online form.
ENDS
We’re making good progress with our emergency repair works in central Sandwich, near the Quay.
Our teams continue to follow the advice and recommendations from the Government and health authorities to ensure that they are able to continue working safely while respecting social distancing measures.
We’d like to thank the local community for their patience and understanding while we carry out this essential work.
What’s happening ?
Central Sandwich, near the Quay – We’ve drilled two new independent river crossings; one to replace the damaged Bulwark main, serving Sandwich, and a second to provide additional resilience for the Golf Road main, serving Deal, which also runs underneath the river.
Latest update:
A256 by Discovery Park – The southbound carriageway of the A256 fully re-opened on Sunday 29th March.
Latest update:
Further re-lining works, which will provide additional resilience to the two pipes running underneath the road, will take place following the conclusion of our repairs at the Quay.
Keep updated
Further updates are being provided via our social media channels and a dedicated page on our website at: southernwater.co.uk/a256-sewer-repairs
Supporting customers during Covid-19
We’ve expanded the support available for customers during the current pandemic. These measures are in addition to the support we already offer. For further information, please see the attached pdf or visit our website here.
Please feel free to share the attached PDF / jpeg image, either via your social media or website, or directly with people you think may benefit from extra help.
Get in touch
If you have any questions or concerns, you can contact our Customer Service Centre on 0330 303 0368 (24 hours – calls charged at local rate) or fill out our online form.
(29/03/20) Update from Southern Water re. Southbound Carriage of A256
We are pleased to confirm that the southbound carriageway of the A256, which has been closed since December 2019, has been fully re-opened this evening.
A single land closure remains on the northbound carriageway to enable further re-lining works which will provide additional resilience to the two pipes running underneath the road.
Work continues in central Sandwich, near the Quay. Whilst continuing good progress is dependent upon the evolving Covid-19 situation, our repairs are currently progressing as expected.
We’ll continue to provide regular updates via social media and via the dedicated page on our website at: southernwater.co.uk/a256-sewer-repairs
(10/03/2020) Latest update from Southern Water - Ongoing emergency sewer repairs in and around Sandwich
We’re working hard to repair a number of complex interrelated sewer main bursts in the Sandwich area.
We’re really sorry our repairs are taking longer than we’d hoped and would like to thank the local community for their patience and understanding whilst we carry out this essential work.
What’s happening?
A256 by Discovery Park - A sewer main burst under a raised section of the A256, near Discovery Park. Due to the complex nature of the pipe’s location, and the road’s Geogrid construction, specialist engineering was required. We are dedicated to fully reopening the road as soon as possible, however safety is the number one priority
Latest update:
Central Sandwich, near the Quay - A burst on the same sewer, directly under the River Stour. To prevent any wastewater flowing in the river, we’re no longer using this pipe. Instead, a fleet of tankers is working in rotation to remove all wastewater flows from Sandwich. We’re working hard to minimise the impact of the tankers – using as few as possible, keeping them out of the town when possible, and imposing a strict 20mph speed limit (10mph overnight).
Latest update:
Keep updated
Further updates are being provided via our social media channels and a dedicated page on our website at: southernwater.co.uk/a256-sewer-repairs
We are planning to have weekly drop in sessions at the Sandwich Guildhall from Wednesday 11 March, between 10am and 2pm. The sessions will then continue every Wednesday, between 10am and 2pm until our work in the area has been completed.
Get in touch
If you have any questions or concerns, you can contact our Customer Service Centre on 0330 303 0368 (24 hours – calls charged at local rate) or fill out our online form.
ENDS
(28/02/2020) Latest update from Southern Water - Ongoing emergency sewer repairs in and around Sandwich
We’re working hard to repair a number of complex interrelated sewer main bursts in the Sandwich area.
We’re really sorry our repairs are taking longer than we’d hoped and would like to thank the local community for their patience and understanding whilst we carry out this essential work.
What’s happening?
A256 by Discovery Park - A sewer main burst under a raised section of the A256, near Discovery Park. Due to the complex nature of the pipe’s location, and the road’s Geogrid construction, specialist engineering was required. We are dedicated to fully reopening the road as soon as possible, however safety is the number one priority
Latest update:
Central Sandwich, near the Quay - A burst on the same sewer, directly under the River Stour. To prevent any wastewater flowing in the river, we’re no longer using this pipe. Instead, a fleet of tankers is working in rotation to remove all wastewater flows from Sandwich. We’re working hard to minimise the impact of the tankers – using as few as possible, keeping them out of the town when possible, and imposing a strict 20mph speed limit (10mph overnight).
Latest update:
Keep updated
Further updates are being provided via our social media channels and a dedicated page on our website at: southernwater.co.uk/a256-sewer-repairs
We are planning to have weekly drop in sessions at the Sandwich Guildhall from Wednesday 11 March, between 10am and 2pm. The sessions will then continue every Wednesday, between 10am and 2pm until our work in the area has been completed.
Get in touch
If you have any questions or concerns, you can contact our Customer Service Centre on 0330 303 0368 (24 hours – calls charged at local rate) or fill out our online form.
(26/2/2020) Update from Southern Water - A256 Road Reinstatement Works
Southern Water’s team, working alongside specialist design and geotechnical engineers, are being mobilised today to begin road repairs on the A256. Southern Water will be working extended shifts to complete the repairs as quickly as possible.
(13/2/20) update from Southern Water – Ongoing emergency sewer repairs in and around Sandwich
Southern Water are working hard to repair a number of complex interrelated sewer main bursts in the Sandwich area.
Southern Water are really sorry this is taking longer than they had hoped and would like to thank the local community for their patience and understanding whilst they carry out this essential work.
What’s happening?
Further updates are being provided via Southern Water social media channels and a dedicated page on their website at: southernwater.co.uk/a256-sewer-repairs
Get in touch
Southern Water customer teams have been on hand at the Quay car park in central Sandwich to answer any questions. Dates and times of when they are available are being provided both their website and via their social media channels on Facebook and Twitter.
If you need to talk to Southern Water, please give us a call on 0330 303 0368 (24 hours) or fill out their online form.
Update From Southern Water
Southern Water are sorry that they had to reinstate the single lane closure on the northbound carriageway of the A256.
Whilst undertaking surveys to assess the road’s integrity, a further issue has been identified on a second sewer pipe which takes wastewater flows from the Deal area – the two sewer pipes run in parallel underneath the same section of the road. Additional tankers have been brought in to manage wastewater flows and protect the environment whilst Southern Water carry out the necessary repairs. Tanker movements will be most notable at the site of our repairs on the A256 and at Golf Road Wastewater Pumping Station in Deal. There will be no impact on Southern Water ongoing activities near the Quay in Sandwich.
Southern Water expect to complete the additional repairs by the end of the week, following which they will be working closely with KCC Highways to reinstate the road as quickly as possible.
Southern Water are continuing to provide regular updates on the situation via social media updates and a dedicated page on their website at: southernwater.co.uk/a256-sewer-repairs
This email and any files transmitted with it are confidential and intended solely for the use of the individual or entity to whom they are addressed. If you have received this email in error, please notify the sender on the details above. To view how we hold your data please view our privacy policy by visiting our website.
4th February update from Southern Water
Ongoing emergency sewer repairs in and around Sandwich
Southern Water are working hard to repair a number of complex interrelated sewer main bursts in the Sandwich area.
Southern Water are really sorry this is taking longer than we’d hoped and would like to thank the local community for their patience and understanding whilst Southern Water carry out this essential work.
What’s happening?
• A256 by Discovery Park - A sewer main has burst under a raised section of the A256, near Discovery Park. Due to the complex nature of the pipe’s location, and the road’s Geogrid construction, specialist engineering is required. Southern Water is working in partnership with Kent County Council highways and are dedicated to fully reopening the road as soon as possible, however safety is the number one priority.
Southern Water have completed our repairs on a damaged section of sewer sitting underneath the A256. Although Southern Water cannot reintroduce pressurised flow to test the repair due to emergency works on the same stretch of pipe under the River Stour, near The Bulwark.
Surveys to assess the road’s integrity are now underway – the results of these surveys will allow Kent County Council Highways to decide on when the road closure can be removed.
• Central Sandwich, near the Quay - A burst on the same sewer pipe, directly under the River Stour. To prevent any wastewater flowing in the river, Southern Water are no longer using this pipe. Instead, a fleet of tankers is working in rotation to remove all wastewater flows from Sandwich. Southern Water is working hard to minimise the impact of the tankers – using as few as possible, keeping them out of the town when possible, and imposing a strict 20mph speed limit (10mph overnight).
Southern Water are preparing to drill under the riverbed to lay a completely new pipe. Due to the location within a Scheduled Monument, Southern Water cannot start major digging until all permissions are in place. Southern Water are working closely with Historic England to get started as soon as possible. Preliminary work is underway.
Southern Water are also exploring a temporary solution which may mean Southern Water can reduce or remove the need for tankers – right now, they are the only way Southern Water can maintain wastewater services and protect the environment.
Southern Water are providing regular updates on the progress of our repairs via social media updates and a dedicated page on our website at: southernwater.co.uk/a256-sewer-repairs
Get in touch
Southern Water customer teams have been on hand at the Quay car park in central Sandwich to answer any questions. Dates and times of when they are available are being provided both on Southern Water’s website and via social media channels on Facebook and Twitter.
If you need to talk to Southern Water, please call 0330 303 0368 (24 hours) or fill out the online form.